Update on December 03, 2024: The Communication Company is scheduled to relocate the cable on Wednesday, December 4, 2024. Able Construction will replace the damaged sewer lateral with a new one on Thursday, December 5, 2024, or Friday, December 6, 2024
Background: On Tuesday, November 19, 2024, an emergency sewer lateral repair was conducted at 2330 Bailey Ave. The sewer lateral was damaged by a communication company during the installation of a communication cable. BSD staff performed a temporary repair to restore sewer service to the customer. District field staff distributed door tags to the affected neighbors to notify them about the repair and construction work. The District is currently working with the communication company to relocate the cable. Once the cable is moved, the damaged sewer lateral will be removed and replaced with a new service lateral.
Sewer Lateral Damage Caused by Cable:
Temporary Sewer Repair and Service to Lateral Restored: